Aqueduct Ciudad de Juarez
Project: Proposed modification of the tank interconnection line
Start date: September 2020
Activities: Trench opening, Carrying of demolition product material, Pipe laying, Welding application, Application of interior and exterior coating, Preparation of bed, pre-capping and covering in compaction of first layer and second layer 90% proctor, Hydrostatic test